Upon the completion of the Crystal Airport Long-Term Comprehensive Plan (LTCP) in 2017 and a joint Environmental Assessment/Environmental Assessment Worksheet (EA/EAW) in 2019, construction of Crystal Airport improvements began in mid-2020. This webpage will provide regular updates on the construction activity.

The improvements at Crystal Airport include the following elements:

  • Decommission Runway 14R/32L and convert it to a full parallel taxiway for primary Runway 14/32
  • Convert portions of primary Runway 14/32 blast pads to usable runway for a total published length of 3,750 feet
  • Shift primary Runway 14/32 approximately 115 feet to the northwest along its centerline
  • Reduce the length of existing Runway 06R/24L (turf) to 1,669 feet
  • Revise the Runway 14 instrument approach procedure and establish a GPS-based procedure to Runway 32
  • Replace the Runway 32 visual approach slope indicator (VASI) with a precision approach path indicator (PAPI)
  • Relocate the Runway 14/32 runway end identifier lights (REILs)
  • Adjust and extend the runway and taxiway edge lights to correspond with the proposed primary runway length
  • Convert Taxiway E into an apron edge taxilane between Taxiways A and E1
  • Remove the section of Taxiway E that crosses Runways 06L/24R and 06R/24L
  • Remove Taxiways E2 and E3 and replace them with a single new connector
  • Add a connector taxiway between Taxiway E and the future parallel taxiway
  • Remove existing runway end connector Taxiways E1 and E4 and replace with new connectors
  • Add new engine-run up pads on either end of Runway 14/32
  • Construct on-airport perimeter roads to allow ground vehicles to circulate without crossing runways – South Service Road with 2020 project, north and west roads future project.
  • Expand the FBO apron to increase tie-down spaces for aircraft and remove tie-downs from the Runway 06R RPZ – Not part of the 2020 project.
  • Release certain airport property for non-aeronautical use along 63rd Avenue North – In progress, but not part of the 2020 project.

The construction activity is divided into five phases:

  • Phase 1: Txy pavement removal  (late July, 2020)
  • Phase 2: Runway 14L/32R improvements (August, 2020)
  • Phase 3: Runway 14R/32L converted to Txy G and South service road construction (late-August through mid-October, 2020)
  •  Phase 4: Airfield electrical improvements (TBD)
  • Phase 5: Electrical vault construction (mid-July through mid-October, 2020)
Crystal Airport Construction Schedule 2020

Subscribe for updates!

Click to sign up. 
Subscribers will be sent regular construction updates.

Construction Project Updates

December 2020 Update

October 2020 Update

August 2020 Update

Construction Notice