The purpose of the project outlined in the EA/EAW is to:

  • Address failing, end-of-life infrastructure;
  • Enhance safety for airport users and neighbors; and
  • Improve facilities for the family of aircraft using the airport.

Overall project objectives

  • Simplify the airfield layout
  • Provide adequate runway length for aircraft currently using the airport
  • Provide aircraft with enhanced arrival capabilities, while minimizing airspace obstacles to the main runway
  • Improve airfield roadways for airport vehicle circulation
  • Expand the airfield apron for additional aircraft parking
  • Develop airport-owned property that is not used for airport operations for other uses
  • Keep Runway Protection Zones (RPZs) on airport property, if possible

Proposed project components

  1. Decommission Runway 14R/32L and convert it to a full parallel taxiway for primary Runway 14/32
  2. Convert portions of primary Runway 14/32 blast pads to usable runway for a total published length of 3,750 feet
  3. Shift primary Runway 14/32 approximately 115 feet to the northwest along its centerline
  4. Reduce the length of existing Runway 06R/24L (turf) to 1,669 feet
  5. Revise the Runway 14 instrument approach procedure and establish a GPS-based procedure to Runway 32
  6. Replace the Runway 32 visual approach slope indicator (VASI) with a precision approach path indicator (PAPI)
  7. Relocate the Runway 14/32 runway end identifier lights (REILs)
  8. Adjust and extend the runway and taxiway edge lights to correspond with the proposed primary runway length
  9. Convert Taxiway E into an apron edge taxilane between Taxiways A and E1
  10. Remove the section of Taxiway E that crosses Runways 06L/24R and 06R/24L
  11. Remove Taxiways E2 and E3 and replace them with a single new connector
  12. Add a connector taxiway between Taxiway E and the future parallel taxiway
  13. Remove existing runway end connector Taxiways E1 and E4 and replace with new connectors
  14. Add new engine-run up pads on either end of Runway 14/32
  15. Construct on-airport perimeter roads to allow ground vehicles to circulate without crossing runways
  16. Expand the FBO apron to increase tie-down spaces for aircraft and remove tie-downs from the Runway 06R RPZ
  17. Release certain airport property for non-aeronautical use along 63rd Avenue North

The graphic below depicts the project.