Dates - 2026-2027

Cost - $10,100,000 CIP budget

Description - Relocate rideshare zone and add a fifth traffic lane to alleviate vehicle congestion and improve overall activity in front of Terminal 2.

Roadway expansion:

  • Removal and modification of current landscaping, sidewalk, curb, gutter and utilities closest to parking ramp
  • Construction of fifth concrete lane on southwest side of roadway
  • Update utilities and lighting
  • Maintain minimum of three lanes during all phases of construction
  • Install new landscaping

Terminal 2 rideshare relocation summary:

  • Prior to road construction, relocate current pickup and drop off location to 2nd level of Purple Ramp
  • Update rideshare wayfinding