34th Ave. South Reconstruction
34th Ave. South Reconstruction
2026-2027
$16.75 million CIP budget
Reconstruction of 34th Ave. South, the major roadway providing access to Terminal 2 from Interstate 494.
Project Summary:
2026
- Concrete curb and gutter repairs
- Installation of pedestrian ramps
- Traffic signal maintenance
- Utility improvements
2027
- Mill and overlay asphalt pavement between 1-494 and Terminal 2