E 70th Street Reconstruction
Timeline: June 3, 2024 - October 2024
Construction Cost: $1.2 million
Description: Reconstruct E 70th Street roadway and install a bike path.
Project Summary
-
Reconstruction of E 70th Street roadway
-
Installation of a new bike lane and walking path
-
Storm sewer improvements and fire hydrant installation
Project Impacts
-
Crews will work on one lane of the roadway at a time while maintaining east-bound vehicular traffic flow from Terminal 2 (34th Ave S.) to Post Road throughout the project.
-
Post Road will maintain two-way traffic from MN-5 through the West Cell Phone Waiting Lot.
-
Access to E 70th Street to Terminal 2 will be redirected to MN-5 W to 34th Ave S.
-
Traffic control measures and detour signage will be in place to guide motorists and maximize safety.
-
Customers will be able to access Signature Aviation throughout the project from 34th Ave S.