Lake Elmo

small plane

An easy drive to the St. Paul business district or to scenic destinations along the St. Croix River, such as Stillwater, Minnesota and Hudson, Wisconsin, Lake Elmo Airport is conveniently located for both business and leisure travelers. The airport is served by a fixed base operator and an aircraft maintenance provider. Lake Elmo Airport has two runways. Runway 14/32 is 2,850' x 75', while 4/22 measures 2,497' x 75.' There are two non-precision instrument approaches to the airport, which has no control tower. Fueling, flight training and aircraft maintenance services are available from a fixed-base operator.

The airport has a total annual economic output of $12.8 million and supports 60 jobs, including 14 directly tied to on-airport businesses.

There are 189 aircraft based at Lake Elmo Airport and in 2018, there were 31,693 landings and takeoffs.
 

Economic Impact

Direct Jobs:                         14
Total Jobs:                           60
Total Economic Output $12.8 million
 

Airport Improvements

The Lake Elmo Airport long term planning process and its associated environmental assessment are now complete. The entire process took place between mid-2015 and November 2018 and resulted in the Federal Aviation Administration's finding of no significant environmental impact. 

The next step in making improvements to the airport is now underway - preparing construction documents for the bidding of work to begin in late 2019.

In summary, planned improvements between 2019 and 2021 include:
  • Construction of a new main runway in a location several hundred feet northwest of its current location
  • Realignment of 30th Street North to accommodate the new runway's protection zone
  • Converting the old  runway into a taxiway and reconfiguring other taxiways 
The airport has not received any significant improvements over the 50 years since the MAC took ownership. These projects will bring the airport's infrastructure up to today's standards in its category. 

Long Term Planning Documents 

The Lake Elmo Airport 2035 LTCP has been finalized and can be downloaded here. Volume 1 contains the report. Volume 2 includes the appendices, including the public comments (and responses) received as part of the community and stakeholder engagement process.  All documents are in PDF format and require Adobe Reader© software to read or download.


Volume 1 - Lake Elmo Airport Final 2035 LTCP: Narrative Report
Volume 2 - Lake Elmo Airport Final 2035: Appendices 1-8
Volume 2 - Lake Elmo Airport Final 2035: Appendix 9 - Public Comments